How to do COPA revenue planning with SD pricing procedure when we have multiple Pricing Procedure

0 Kudos

Hi Experts,

I'm now to COPA Revenue planning, so could you please clarify me on below issue:

Client had a 10 Pricing procedures and these 10 pricing procedures assigned in KE4U- Valuation strategy in order to get the Revenue values into KEPM Planning.

Issue is in KEPM - When I execute ' Execute Method' option for respective Parameter set under Planning Method, Revenue value was valuated 10 times of actual Revenue value.

What I have customized:

I have assigned all of 10 Pricing procedures in KE4U valuation strategy.

As per my understanding, here Revenue value is valuated for each one of Pricing procedure (KE4U - Plan valuation strategy)

Could you please assist me on Revenue Planning when we have multiple pricing procedures for one Sales Organisation/Co.Code(s).

And please suggest me if having any other better ways to do Revenue planning in COPA.

Regards,

Shiva

Accepted Solutions (0)

Answers (2)

Answers (2)

0 Kudos

Hi Homann,

Thanks for your prompt reply!

i).I have assigned Valuation Strategy to PV:03&04 in KE4U

ii). KEPM Screen shot: (attached)kepm-screen-shot.jpg

Please note that as of now I have assigned only 4-SD pricing procedure in Valuation strategy KE4U.

And out of 4 pricing procedure, 3 pricing procedures contain the VPRS (Std Cost=405.02) condition and those also Cost was calculated 1,215.06= (3*405.20)

PR00 - Revenue was maintained for the combination of Customer + Product = 1000 and it was calculated

As 4,000= (4*1000)

iii). CE2xxxx screen shot:(attached)ce2-table-screen.jpg

iv).The below chain link query would be additional concern:

And Client had a requirement that, they want to generate the Revenue plan values automatically by uploading quantities values at huge level.

Here my challenge is PR00's Price, Price has been valuating when filled / Accessed Sales Org, Distr channel, Customer and Material.

Client has 5 Distr channels. In KEPM Distr channel has to fill in order to get Revenue, maintaining Distr channel at Customer & Product level will generate 5 line items. Is there any way to skip the Distr channel field in order to get the Revenue from SD? [ you can see in 1st screen shot].

So please suggest me to overcome on above concerns.

Your prompt reply will helps me a lot.

Thanks & Regards,

Shiva T

hohoman
Active Participant
0 Kudos

Hello,

pls do not think I want to be impolite but do you assigned the strategy tot he correct Point of valuation?

Could you pls add screens of KEPM and the planning line-items you posted until now ( Table CE2[your OPC])

Regards

Holger

0 Kudos

Hi Homann,

Thanks for your prompt reply!

i).I have assigned Valuation Strategy to PV:03&04 in KE4U

ii). KEPM Screen shot:


Please note that as of now I have assigned only 4-SD pricing procedure in Valuation strategy KE4U.

And out of 4 pricing procedure, 3 pricing procedures contain the VPRS (Std Cost=405.02) condition and those also Cost was calculated 1,215.06= (3*405.20)

PR00 - Revenue was maintained for the combination of Customer + Product = 1000 and it was calculated

As 4,000= (4*1000)

iii). CE2xxxx screen shot:

iv).The below chain link query would be additional concern:

And Client had a requirement that, they want to generate the Revenue plan values automatically by uploading quantities values at huge level.

Here my challenge is PR00's Price, Price has been valuating when filled / Accessed Sales Org, Distr channel, Customer and Material.

Client has 5 Distr channels. In KEPM Distr channel has to fill in order to get Revenue, maintaining Distr channel at Customer & Product level will generate 5 line items. Is there any way to skip the Distr channel field in order to get the Revenue from SD? [ you can see in 1st screen shot].

So please suggest me to overcome on above concerns.

Your prompt reply will help me a lot.

Thanks & Regards,

Shiva T