Hi all,

I have the following scenario:

I sell product A that is managed MTO. This product A is procured externally though an subcontracting purchase order.

On the subcontracting purchase (L). I send 2 components (B and C) to the subcontractor.

Product C is procured externally and is managed in MTS (no problem!)

The point is that Product B is procured in house (production order) with special procurement type E, MTO scenario! I can produce this material with MTO and have it in MTO stock, but how can I send it to the subcontractor?

Note that I really need to segment materials A and B by customer order. ThatÂ’s why I use MTO due to business constraints. This is a scenario that Product A and component B have special dimensions defined on the sales order (configuration), and I can only use these materials on that sales order.