Settlement of Process Orders, Selection of more than one Plant

Hi,

we have two plants within the company code. When calculating overhead, WiP, variances and settling the process orders, using the collective processing, it is only possible to enter one plant.

Is there a possibility to select two plants?

Thanks for help.

Regards, Marc

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Apr 11, 2008 at 01:14 PM

    Hi Marc,

    Have you tried using the background programs?

    Variances = RKKKS1N0

    Settlement = RKO7CO88

    Unfortunately for WIP I'm not sure if multiple plants are allowed. Program SAPKKA07BG is equivelent program to those above but it does not allow more than one plant.

    Hope it helps somewhat.

    Elaine

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.