on 04-11-2008 11:43 AM
Hi,
we have two plants within the company code. When calculating overhead, WiP, variances and settling the process orders, using the collective processing, it is only possible to enter one plant.
Is there a possibility to select two plants?
Thanks for help.
Regards, Marc
Hi Marc,
Have you tried using the background programs?
Variances = RKKKS1N0
Settlement = RKO7CO88
Unfortunately for WIP I'm not sure if multiple plants are allowed. Program SAPKKA07BG is equivelent program to those above but it does not allow more than one plant.
Hope it helps somewhat.
Elaine
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.