HI Gurus,

I have a senario in which,

I have created sales order in VA01,

I have done outbound delevery VL01N, Inspection lot is generated while doing picking.

I want to disable the Post goods issue tab in VL01N so that the inspection lot is cleared and certificate is printed and then only this tab ( Post goods Issue ) tab should get activated.

Otherwise it should be activated in VL02N.

Else is there any control other than this to post the goods issue so that the goods issue should only be done after clearing the inspection lot. Is there any user exit to suit this senario...

Thanx in advance

Praveen Kumar

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Apr 11, 2008 at 12:05 PM

    Until the lot is posted and cleared you can't "clear" the lot. It sounds like your trying to send out the material prior to the lot being completed. This is not possible when you've created this type of lot. The whole point of the lot is to complete tests prior to shipping it out.

    Craig

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.