MRS Planning Board

Hi,

Created a Work order with multiple operations and assigned various work centers for those operations.

When I try those operations in Planning board it is not visible as because I am using the t.code /MRSS/PLBOORG for executing the MRS Planning board. In that the demands are selected based on the Operation work centers.

Is any other way to fetch the various operations of the planning with various Operation work center apart from Org. level planning.

Thanks & Regards,

Swami

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jan 30 at 09:49 AM

    Please use transaction /MRSS/PLBOORGSRV here you can specify multiple org units.