Skip to Content
0
Former Member
Apr 10, 2008 at 04:18 PM

Program is available in Dev client but not in Production client

20 Views

Hi experts,

I am facing this problem in PO Print preview in Production server as we are ready for Go live Monday. I did all the request transports from Development to Production. We are using ECC 6.0

In ME21N if i click the Print preview button system is not showing the print preview but showing this message

Processing routine ENTRY_NEU in program /SMB40/FM06P does not exist.

But the same is working fine in Development/Sandbox/Quality server. we have not faced any problem.But why is not same appearing in Production. Is this settings a client dependent.

All the details are maintained in the MM configuration NACE--Ouput type -- all i assigned the Smart form also.

If I check this Program /SMB40/FM06P in SE38 it shows it doesnot exist.How come this is possible as in Development/Quality this program is there but in Production this program does n't exist.

I am really surprising how this program is missed in Production client. But it is available in Dev/Quality/Sandbox.

I searched some SAP notes 968332 in that it says we have to install some transports. Is it required to install or is there we can copy the program from Development to Production client.

Please help me on this issue.

rgds

Swamy