Hi,
I have a task list with a material BOM for the operations, in this case when i do a maintance order with reference at the task list the text of the material BOM don´t copy to the order.
In the material BOM, I put text in the item by using the fields POTX1 and POTX2 in the sheet "status/Lng Text", but the second text doesn´t transfer to the maintance order. I will hope that the second text appear in the long text of the order.
What happen with the second text??
Thanks in advance,
Hi,
Surely long text will copy to order components if u have maintained correctly becuase ther is no any check.
Let me send the screen shot long text maintain and order screen
Regards
Sendil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.