Apr 10, 2008 at 08:21 AM

Purchase order for project

35 Views

Hello together,

We have a one senerio. At my client end no. of project is going on. We do not have sales order for the project parts. Presently we are creating purchase order with acct.assignment P ( WBS Element ) but our mamangement asking me to have the stock of the material purchased against WBS element. But it is not possible the combination of WBS element with storage location.

How can i create PO where no WBS element but i could get the stock of the material

Is there any work around?

Thanks in advance.