I have two prod version: everything identical except the Routing and hence the prod line is different.

The BOM is also same. 0001 and 0002: same valid date and qty etc.

Once in a while, when I create manual Prod Order in CO01, it will use 0002, instead of 0001.

Thoughts? it should select always 0001 by default. if needed we would change it to 0002. 90% of the time it will do 0001, 10% 0002. Forward scheduling.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

3 Answers

Darrell Hart Dec 22, 2017 at 02:04 AM
0

Check the setting in MRP4 tab for Selection Method.

Should be set to 3

Share
10 |10000 characters needed characters left characters exceeded
Oleg K Dec 22, 2017 at 12:40 AM
0

run c223 and check the following values:

1.task list type

2.task list group

3.task list group counter

make sure your 0001 and 0002 have correct sequences

Share
10 |10000 characters needed characters left characters exceeded
Anupam Sharma Jan 02 at 08:39 AM
0

Hi

Use quota management in order to distribute the quantities in the required percentage in order to generate planned order in respective ratios through MRP. For manual creation of production order select the manual selection of production version in order type dependent parameters in order to select the PV in production order creation.