In PPOM_OLD, we have an organizational unit (I'll call this org unit 2) with a "reports to" relationship to some other organizational unit (I'll call this org unit 1). I need to change the "reports to" for org unit 2 to a new org unit (I'll call this org unit 3). Org unit 3 already exists. Org unit 2 has other org units and cost centers with positions and employees already assigned.

Questions:

Can the "reports to" for org unit 2 be changed to org unit 3?

If it can, do all the org units, cost centers, positions and employees follow?

What actions need to be run on all the employees to properly reflect the reporting structure to org unit 3?

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Ram

(1) Yes, org unit 2 can be changed to org unit 3. one way you can do is : PO10 ==> Select "org unit 2 " ==> Relationships ==> Change "Reports to" from Org Unit 1" to "Org Unit 3"

(2) Yes, all cost center, positions under Org Unit 2 will follow and be under Org Unit 3.

(3) You can check #2 with PPOSE

Regards,

Jim