Dear All,
We have created the new activity type and assigned the secondary cost element. When we try to change the allocation cost element in KP26, is not possible. Because the field is graved out. How we change the allocation cost element in planning layout. The user has wrongly assigned the another cost element during the creation of activity type and we want to assign in exact cost element.
Please give your reply.
Thanks with regards,
Ranesh.
Dear Ranesh ,
You cannot change it directly at KP26 . You will have to change it at the master data level . Go to the Activity Type and change the Allocation Secondary Cost element first .
Please assign full points .
Regards
Deepesh S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
9 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.