Skip to Content
avatar image
Former Member

SNP Planned Order entered manually in Planning Book is ignoring the Resource Capacity

Hello Team,

I'd like to know if the following scenario is a standard system behavior.

We are currently using SNP Heuristics followed by CTM and Deployment. In the SNP Planning book when a Planned Order is entered manually it is ignoring the resource capacity. ( PDS for Product Location has the resource assigned).

Example- Weekly Bucket Capacity - 700 Qty

Say If I enter a manual Order for 1000 the system is defaulting it to a Single day having the Same Start and End Date displayed in the Details Section and in the resource view the weekly bucket displays an overload.

Question - Is this the Standard SAP behavior or should it consider the resource capacity and distribute the order having a different end date.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

0 Answers