Material master transfer

41 Views

Hi guys,

After transfering material master from ECC to APO

Checking horizion and ATP group not matching with ECC data .

For example i have planned delivery date as 50 days where as checking horizon is 20 days in APO , Could any one explain me the route cause for this?

Thanks and regards

Thamizhchelvan G