i m going to perform remote client copy from production to sandbox how to enable parallel processing before that .

and its is hugh client and i want to do it fast can i start it in Foreground and if yes what parameter i have to set to what value to do it in foreground

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Apr 08, 2008 at 10:34 AM

    Hi,

    First start your remote client copy as a background activity.

    Also no user should be logged on to the source client making any kind of changes.... customising or transaction....

    To enable parallel processing read the following

    SAP Note : 541311 - CC-INFO: Parallel processes FAQ

    Do reward points if the answer is helpful.

    Regards,

    Suhas

    Edited by: Suhas Ajgaonkar on Apr 8, 2008 4:04 PM

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 08, 2008 at 10:16 PM

    hi!

    When you do a remote client copy you should set the parameter below on source and target system, because system uses dialog processes.

    rdisp/max_wprun_time=0

    For parallel processing you need to have dialog processes.

    Cheers

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 09, 2008 at 08:37 AM

    Hi Bhupinder,

    Try following if this could help you , first ensure you have enough number of wp free , then in remote client transaction select parrallel processor under goto menu , here you can choose number of wp, it also allow you to choose logon group as well ( in case you have multiple servers and logon group maintained.)...

    Cheers

    Add comment