Skip to Content
avatar image
Former Member

Material to material transfer (different BUM)

Hi all,

I have a question: How can I transfer material stok in KG to another material in ST?

I tried to use 309 mvt type, but the error "Stockkeeping units KG and ST differ" occurred.

Thanks and regards,

Peter

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

4 Answers

  • Best Answer
    avatar image
    Former Member
    Apr 08, 2008 at 06:29 AM

    Hi

    The rule for 309 movement type is that the Stock keeping units of both the materials should be the same.

    So for carrying out the Process you need to maintain both the materials in same Base UOM.

    Thanks & Regards

    Kishore

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hello Peter,

      Do you think of the value at which the booking will be realized? SAP uses standrad price (if you maintain SP) / MAP, so you needn't give any value.

      Of course the goods have to have the same SP if you want to have balance of 0 at the end of your action.

      BR

      Csaba

  • avatar image
    Former Member
    Apr 08, 2008 at 06:27 AM

    How can you transfer if one material is in "KG" & other in "ST"..

    for transeferring material through 309 mvt , the units must be same.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 08, 2008 at 06:32 AM

    Hi Peter..,

    Maintain alternative unit of measure for the material and equate it with Kg.

    regards.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 08, 2008 at 07:19 AM

    Hello Peter,

    As you said, Material 1 is measured with KG and Material 2 is measured with ST. But let me know these two units of measure are base unit of measure or order unit. Please confirm the above.

    If both materails unit of measure (i.e. you mentioned UoM) is base unit of measure means. You can do the material to material stock transfer, once after you maintain the conversion factor of unit of measure in the material master. (i.e. Goto Additional Data in the Material master through change materail master MM02. And give the conversion between these two UoM's and then try for the M to M transfer through T.Code: MB1A, with Mvt.type. 309.

    Suggestion: But, I don't think it is possible (i.e. M to M transfer with each different UoM). However you just try for the above process and will make you understand.

    Hope this will clarify you,

    Reward, if it helps,

    Regards,

    Srin.K

    Add comment