How is it possible to get multiple purchase req for a material which has following settings
zero stock, subjected to procurement from another plant thru STO.. and requirements are fed thru end customer Sales order(no forecast, no PIR).
i.e If i get requirement for that material thru 3 SO then I want to three purchase requisitions created after MRP run.
Please give your valuable suggestions.
You need to create a MTO secenario and stg 20 in material master
Then in the material master you need to have a special procuremnet key in MRP2 so that you define from which plant the material will e delivered.
Hence when you run MRP, system will create PR for each SO. and this PR you can convert into 2 STO.
please come back if required
Hi,
If you want to maintain in MTS material, do the following setting:
1. Your plant stock is zero. Production against sales order. So use strategy 40 in mrp 3 view. In this system will allow you to create PIR. But you have to control.
Strategy 20 only used for MTO material.
2. For stock transport order, maintain material master in alternate plant. Maintain spl.proc key 40 in mrp 2 view in main plant.
3. To create multiple P.R, maintain individual/ collective indicator - select individual req only in mrp4 view of material master in the main plant.
Regards,
Dharma