How is it possible to get multiple purchase req for a material which has following settings

zero stock, subjected to procurement from another plant thru STO.. and requirements are fed thru end customer Sales order(no forecast, no PIR).

i.e If i get requirement for that material thru 3 SO then I want to three purchase requisitions created after MRP run.

Please give your valuable suggestions.

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Apr 07, 2008 at 06:16 PM

    You need to create a MTO secenario and stg 20 in material master

    Then in the material master you need to have a special procuremnet key in MRP2 so that you define from which plant the material will e delivered.

    Hence when you run MRP, system will create PR for each SO. and this PR you can convert into 2 STO.

    please come back if required

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Rajesh,

      The main idea is to track end customer SO in issuing plant. If I have it based on PIR then I dont know what is in end customer SO. The issuing plant will make the delivery and paking specific to end customer

  • author's profile photo Former Member
    Former Member
    Posted on Apr 07, 2008 at 06:16 PM

    Hi,

    If you want to maintain in MTS material, do the following setting:

    1. Your plant stock is zero. Production against sales order. So use strategy 40 in mrp 3 view. In this system will allow you to create PIR. But you have to control.

    Strategy 20 only used for MTO material.

    2. For stock transport order, maintain material master in alternate plant. Maintain spl.proc key 40 in mrp 2 view in main plant.

    3. To create multiple P.R, maintain individual/ collective indicator - select individual req only in mrp4 view of material master in the main plant.

    Regards,

    Dharma

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 08, 2008 at 04:27 AM

    hi sridhar ,

    check with the availability group in mRP3 as individual requirement.then u will individual PR for the sales order.

    Reward if useful

    Amit

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.