on 04-03-2008 7:18 AM
Dear Friends
I wanted to know the relevance of Field--- Material Orgin in Costing-1
view.
as we are planning to start standard costing & change our price control
from V to S,so please update me the importance & also in costing -1 view we have field Origin Group
Whats the importance of this field.
Regards
Sandeep Patil
Hi Patil..,
For Qurrey 1:
If you set this indicator, the costs incurred will be updated under a primary cost element and with reference to the material number
This enables you to analyze material costs in the information system more detail.
For Qurrey 2:
Changing the Price Control indicator from V to S. for semifinished materials (In House Produced) keeping S is the best practice. and you can keep V for Raw materials or Procured materials.
regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.