Hi Friends,
I have allocated defferent persons to Defferent WBS elements. Now i want to see, How the workforce has been allocated?pl respond in detail ....urgent please
Do you mean you assigned individuals to WBS elements as Project Team Members
Or have you assigned splits (individuals) in the Person Assignment Tab of the Internal Network Activity
If the latter you can use transaction CMP9 to view
You can also use CMP2 and CMP3 to assign the splits to the Network Activities
If the former - I don't think there are any standard reports showing this detail (but would be happy to stand corrected)
Regards
Steve