Dear all

Facing problem after Changing "Inspection point" of material.

There are different Plants and materials.So i create a new inspection point and add it in Routing of One materials in one Plant .After this when new inspection lot of that material generated and data is saved in new inspection point then the same inspection point is displayed in all material in all plants.

So the problem is by changing inspection point of one material it displayed in all mateial in all plants.How to aviod this problem? So new inspection point only reflects in one material not all material in all plants.