Hi Gurus,

I am trying to change a Profit centre in a Work Order via IW32 as Profit Centre is greyed out.I know it has to done via changing the Functional Location.But although i have changed Function Location still Profit Centre remains unchanged..

Is there any way to change Profit Centres in WOs?

Also please let me know are there restrictions on WOs status for changing Profit centres?

please help me its very urgent.....

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Apr 01, 2008 at 09:33 AM

    hi

    The system proposes the profit center in the cost center belonging to the responsible work center. You can overwrite this, however.

    If you change the responsible work center in the order, the system does not automatically overwrite the profit center on the additional data header screen. If required, change this manually.

    You can change the profit center in the order, provided that no actual data exists for the order yet

    regards

    thyagarajan

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.