on 04-01-2008 8:40 AM
Hi Gurus,
I am trying to change a Profit centre in a Work Order via IW32 as Profit Centre is greyed out.I know it has to done via changing the Functional Location.But although i have changed Function Location still Profit Centre remains unchanged..
Is there any way to change Profit Centres in WOs?
Also please let me know are there restrictions on WOs status for changing Profit centres?
please help me its very urgent.....
hi
The system proposes the profit center in the cost center belonging to the responsible work center. You can overwrite this, however.
If you change the responsible work center in the order, the system does not automatically overwrite the profit center on the additional data header screen. If required, change this manually.
You can change the profit center in the order, provided that no actual data exists for the order yet
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.