urgent.. planning run....

Dear Friends,

In PS how to carry out the planning run. we are getting the error of " project doesn't allow individual project production". is there any pre setting from MRP point of view.Pl help.will be awarded

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Apr 01, 2008 at 05:41 AM

    Hi,

    In order to do MRP run at project level following details are required

    1. Material Components need to be assigned to network activity of Projects

    2. Project Status to be in Release stage.

    3. MRP run in transaction MD51

    There is no specifc settings required for MRP run at project level as it is SAP standard functionality.

    Hope this will help you.

    Best Regards,

    Rakesh Pradhan

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      One more thing in your material master should have considered for MRP planning. This you can check in MRP-1, mrp type.

      Please change your stock type as valuated / Non valuated stock as non stock may be n't considered for MRP run.

      Hope this will help you.

      Best Regards,

      Rakesh Pradhan

  • author's profile photo Former Member
    Former Member
    Posted on Apr 01, 2008 at 05:47 AM

    Hi,

    It means you have not maintained any project stock. In CJ20N, check under 'Control data' tab what radio button is selected under project Stock section. I think it must be No stock.

    Regards

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      I think you will be able to change the indicator to 'Non valuated' stock for the current project. Then MRP should work. In order that all new projects should not have 'No stock' change the Project Profile accordingly.

      Please understand that by selecting Non valuated stock, your stock will not have value, ie during GR cost will not flow with material. But you dont have any other option as you can no longer select Valuated stock. Refer this link for better understanding of stocks:

      project-stock-type-in-cj20n

      Regards

      Shrikant

      Edited by: Shrikant Rakate on Apr 1, 2008 11:45 AM

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.