We are using PS+PP+SD .We Create Project Creation & Assign FG Creates Res .Parallel to this activity we create Sales order for FG & assign WBS to SO Item.

Issue is that ,during MRP Run with MD51 system is creating planned order for project & SO Both which double my requirement.

What i want that sales order should consume Project Reservation .

Plz suggest

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Caetano Almeida
Dec 13, 2017 at 02:43 PM


You can make the sales order not relevant to MRP by changing the settings under the requirement class/type (transaction OVZG, OVZH, OVZI).


Show 1 Share
10 |10000 characters needed characters left characters exceeded


Project Reservation = 17, Sales Order =12.

After dispatch Qty =1 ,Production order Balance -16 , Sales order Balance = 11.

Issue is that system is creating Pld for SO quantity 12.

Change Schedule Line Item From CP To CN .Means SO Item not relevant to MRP. MD51 not considering delivered Qty 1 and creating Pld during MRP Rerun

After removing SO form MRP System is creating Pld for Dispatch Quantity. Issue is that Planned order should not create in Both cases during MRP Rerun.