Mar 31, 2008 at 12:10 PM

Overlapping in Routing

690 Views

Hi all ,

i have three operations in Routing as follows :

OPR Workcenter setup machine labor

0010 Man1 0 0 600 min

0020 Mach1 0 600 0

0030 Man2 0 0 600 min

Now if i am scheduling forward (all the workcenter available in time 09:30 to 17.30 with ) i tried with required overlapping for all three operation , but with what logic it will overlap ,

As the third operation, starting 09.30 but finishing after 2 days. (it is considering 1200 min )

plz guide .