1. I have a scheduling Agreement (SA), and the qty mentioned against this SA is 1000 (say).

2. Now when i generate schedule lines for this SA (ME38), I am allowed to schedule more than the quantity that's mentioned in the SA.

3. Please advise, is it possible to restrict this behaviour. i.e. I want to give an error message if the Schedule Line qty exceeds the SA qty.

Please advise. Very urgent.

Regards,

Manju.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Manju,

Yes its possible to restrict the case as u mentioned.

Check the below settings:

IMG-MM-Purchasing-Environment data- Define Attributes for system messages

go to meassage no : 00-06-067 set it as Error message.

U'll achieve ur result.

Award points if its helpful

Sangram