Restrict RM batch for goods issue for 2nd order until the 1st one is complete

Hi,

How to restrict the batch from auto proposal in 2nd order until the final issue from1st is done.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Dec 14, 2017 at 03:05 PM

    Hello

    There is no feature in standard to do it. You can use one of the available BAdIs for batch determination to implement this logic:

    https://wiki.scn.sap.com/wiki/display/PLM/Userexits+and+BAdIs+-+Batch+Management

    Regards,

    Caetano

    Add comment
    10|10000 characters needed characters exceeded

  • Dec 18, 2017 at 05:43 AM

    Thanks Caeteno for confirming.