Restrict RM batch for goods issue for 2nd order until the 1st one is complete

Hi,

How to restrict the batch from auto proposal in 2nd order until the final issue from1st is done.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    Posted on Dec 14, 2017 at 03:05 PM

    Hello

    There is no feature in standard to do it. You can use one of the available BAdIs for batch determination to implement this logic:

    https://wiki.scn.sap.com/wiki/display/PLM/Userexits+and+BAdIs+-+Batch+Management

    Regards,

    Caetano

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 18, 2017 at 05:43 AM

    Thanks Caeteno for confirming.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.