on 03-28-2008 9:42 AM
when customer order placed ,in that order partially delivered that order the customer wants to foreclose the order .how it will be happen
what configuration has to be done the sd people.
hi
if a document is partially referred and you want to set the status of the previous doc as completed
then go in change mode of tha source doc and place a reason for rejection for the remaining materials VA02
then automatically the status of the source doc will be complete
you can also configure in the item category
completion rule field : put it as 'A'
regards
ravi
Edited by: ravi chandra on Mar 31, 2008 1:40 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vishal,
I believe, Completion Rule in Item Category works only for referencing Quotations/Contracts and it doesn't work for Orders.
Correct me, if I'm wrong.
Thanks,
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
1st solution is either you go to va02 and put a reason for rejection and close it
2nd solution is that item category TAN , there is completion rule field ,put B and then create a sales order.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Open the order, goto Item and Reject the Items by assigning - Reason for Rejection. This automatically updates the status of that item.
Thanks,
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.