Skip to Content

PM03, I can selectec under CO02

I need create a pourchase requisition for a production order. for service order work good, using SM03 control key, then services tab i can add the services,

but using CO02, don't let me add PM03, the system said:

Control key PM03 is not permitted (check entry)

even i added under OPCG, i added the Schd external op flag.

x3.jpg (45.9 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Dec 13, 2017 at 09:06 PM

    Hello

    Control key PM03 is for PM orders. For a external processing on a production order operation you should use control key PP03.

    Regards,

    Caetano

    Add comment
    10|10000 characters needed characters exceeded

  • Dec 14, 2017 at 08:28 AM

    Hi Johanna,

    add additional explanation on top of Caetano answer. PM03 is for PM order services. You should use control Key starting with PP* for production order.

    The reason you cannot assign PM03 to CO02 is because of Service indicator in PM03. If you un-tick it via OIZ5 then you won't hit error. But as mention above, you shouldn't use this PM03 for production order external processing.

    Thanks

    Add comment
    10|10000 characters needed characters exceeded