Progress Analysis

Dear All ,

While doing transaction CNE5 i am getting , all planned values like plan POC,BCWS but i am not getting actual values like Actual POC ,BCWP.

Inspite of confirming actvities and making service entry sheet up to MIRO.

All other configuration settings are correct.

Is Result Analysis key is to be defined for posting of actual cost.

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Mar 28, 2008 at 09:25 AM

    Probably an obvious question...but did you run CNE1 or CNE2 before CNE5?

    Steve

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Pravin

      We are not using Service Entries here...do you get the same problem if you just post an FI journal cost to the activity/network/wbs (whichever applies)

      I think that you have confirmed that you can now see the Actual POC but just not the BCWP

      Do you have Annual Budget Values for the WBS element?

      Can you see these in CNE5 when selecting the appropriate Budget column?

      Which POC Weighting have you used in your Progress Version

      (perhaps try 3 Budget - Yearly Value)

      Regards

      Steve

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.