Using SAP Business ONE DI API 9.2 in SAP Business One 9.3

How do I change the start and end date of the route/stage in the production order with the SAP Business ONE DI API 9.2 in SAP Business One 9.3

Since SAP Business One 9.3 it is possible to add routes / stages to a production order.

Now I would like to retrieve or change the start and end dates of the routes / stages via DI API, but that seems not to be possible.

Even when I change the start or duedate of the production order via DI API, the start and end dates of the stages remain the same. When I do it in SAP Business One directly, the start and end dates will be changed to the same dates as the start and duedate of the production order.

To retrieve the dates I use a recordset.

But how can I save the dates back to the database (its an SQL database)?

Add comment