Hi,

We have fixed bin stock with just the SKU label which has only the product information.

SKU Label Boxes picks will not be picked into an HU. Please advice me on how to move these boxes to conveyor (Interim storage) and then to the ship lane (destination), where we will be palletizing it.

Also how will the pallet be associated to the proper ODO lines.

Thanks.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Dec 17, 2017 at 12:01 PM

    Hi Sankar,

    Can you please try with below

    1> LOSC: Pick face to ship lane

    2> Putaway Strategy: to determine conveyor (Interim storage) from Pick Face- Pick Task

    Kind Regards,

    Ajit

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Thanks Ajit. So, it does not require HU? Can it be palletized at the end of the conveyor, which would be a drop lane?