I've created a Web Layout based on IP with a copy function (e.g. from actual 2008 to plan2009) over 12 calendar months. For choosing the months to be copied, I created a Variable (calmonths) and added an Input Field into my layout to enter the the months to be copied. I referred the variable to the input field and it's working...
When I want to select several months to be copied, I can type in " 1; 2; 3; " into the input field, execute the planning function and only month 1, 2, 3 (i.e. Jan, Feb, Mar) are being copied. But when I want to copy all 12 months, i have to enter 1; 2; 3; 4;...11; 12 which is kind of anoying! Has somebody some experience whether I can use a value range like 1-12 (or something like that) to avoid entering all the months individually? (I tried 1-12; 1- 12; 1 - 12; 1:12 etc but nothing like this is working)
It would be very helpful if someone has an idea
All the best,
Norbert
Did you try using a variable of type 'value range'?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You should be able to find the variable of type 'Value Range' in the type of variable drop- down.. This will help out.
Regards,
Srinivas.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mayank, hi Srinivas.
Thanks a lot for your valuable input! Unfortunately I was not able until today to test your recommodations.
I tried your Interval variable but then faced the problem that I cannot enter multiple months anymore (e.g. 5 - 8 worked, 1; 3; 5 not). Then I inserted both variables, multiple values & interval, into the planning function as well as in the button group in WAD for executing the PF but was not able to execute the following example: 1; 8; 4 - 6. After trying out for some time I figured out that one has to type in the figures in the following order: 4 - 6; 1; 8. Only then I am able to execute the planning function for the months April-June & Jan & August. So, if you're facing the same problem in the future, maybe you have the solution
Best regards,
Norbert
Hi Norbert,
In the Interval variable, if u want to copy from April to June, give the values as 4-6 (which u said is working for you), and if u want to copy for only Jan, give values as 1-1, and for August give as 8-8.
You need not create both Interval and multiple value variables. Only interval variable would suffice in this case.
Hope this will resolve your problem.
Regards,
Srinivas Kamireddy.
Hi Srinivas,
you are right, I could also do this by entering the month March by 3 - 3. But what we wanted to do is being able to enter single values and also a value range at one into the input field, e.g. 1; 3-5; 11-12.
Right now I got to see, that some characteristics (such as calmonth) are not supporting an interval-section... But I'm able to execute the planning function with one interval and several single values (3 - 7; 1; 11) but not if I only enter an interval section (3 - 7). Here I have to enter it the following way: 3 - 6; 7. Strange, but this is how the system tells me.
Best regards,
Norbert
User | Count |
---|---|
93 | |
11 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.