Unable to do backup scheduling of webi reports in SAP BI server on Oracle Linux

Dec 09, 2017 at 05:43 AM

59

avatar image

Hie gurus,I am unable to do backup scheduling of webi reports to a different folder other than the default location in SAP BI platform hosted on oracle linux.I have put the path for the destination folder in the settings of the adaptive job server for the promotion management service together with the enterprise username and password.However when I schedule the webi report,the following error comes up :Commit Status=Commit attempted and failed., Promotion Status=Failure :Delivery results to destination (CrystalEnterprise.DiskUnmanaged) failed.Is it the issue of rights of the enterprise credentials to write to the destination folder or what?.The SAP BI platform was installed on linux using another user other than root.what might be the problem

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Jawahar Konduru Dec 11, 2017 at 01:33 PM
0

Do you mean you selected "File system" as option while scheduling? If you have selected file system, make sure that directory has access to account which Bo services are running.

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Yes Jawahar.Ok I will look into that

0
Denis Konovalov
Dec 14, 2017 at 09:07 PM
0

Adaptive job server for promotion management is not involved in scheduling webi documents to disk.