Production task commitment - document event

Hi there,

it is possible to document events when committing a production task.

Where can these data be reported?

Kind regards,

Klaus

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Dec 15, 2017 at 09:15 AM

    Dear Klaus,

    Yes it is possible to document events at the time of confirming a production task especially for make and supply tasks and not for check task.

    We can perform Document event by following the steps below

    • Go to the Production Control work center
    • Go to the Task Control view
    • Select the Task and Confirm
    • Select Document Event button
    • Enter the notes and Save

    This data is captured in Production Lot in the Execution Monitor tab

    • Go to the Production Control work center
    • Go to the Monitoring view
    • Select the relevant Production Lot ID
    • Select Edit and go to the Execution Monitor tab
    • Select the relevant task
    • You can see the event type, which you have saved.

    I hope this answers your query.

    Regards,

    Sandeep

    Add comment
    10|10000 characters needed characters exceeded

    • Dear Klaus,

      We have one Data source "Production Task" , Could you please check if this serves your purpose.

      Data Source Name: "Production Task"

      Data Source ID: "SCMPTV01"

      Regards,

      Sandeep