Hi,

I have a query regarding the Maintenance Strategy for performance (counter) based plans.

We need to create a strategy such that the first Order is generated on 19th Jan 2018 with counter reading of 61461. From that point onwards the next reading will be after 2500 hrs i.e. at 63961 then after 1500 hrs at 65461, then again after 2500 hrs at 67961 and then 1500 hrs at 69461 and so on.

I need to understand what I need to enter for Package details in IP11 (Strategy) and once Maintenance Plan(IP42) is created based on the created Strategy then how to schedule in IP10 i.e. what to give in the Start counter reading.

Note: I know how to create Equipment, Task List and Package assignment to Operations for above process

Thanks

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Faisal Khan Mar 07 at 05:07 AM
0

Hi,

Can anyone shed some light on my query?

Thanks

Faisal

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Hi Faisal,

You want to have orders generated 1500 - 2500 - 1500 - 2500.

When you schedule the plan, system will be generating as below screenshot

So you cannot get the alternate option.

Alternate option is Multiple Counter Plan, here you need to have separate counter for 1500 and 2500. Upon scheduling system will behave has expected.

Check this concept in your system

Regards

Terence

capture.png (18.7 kB)
0
avatar image
Former Member Mar 07 at 12:23 PM
0

Hi Faisal,

You will have to create a strategy with package P1- 2500 Hr and P2 - 1500 Hr.

Now when scheduling the maintenance plan, put start counter reading as 61461.

Try it and let me know if it answers your query.

Thanks,
Ashish

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Hi Asish,

I tried to replicate the same but the Next Planned counter reading is falling after 1500hrs first time and NOT 2500hrs as desired. Please see below my steps

strategy.png

Regards

Faisal