Maintenance Plan Strategy - Performance based

Hi,

I have a query regarding the Maintenance Strategy for performance (counter) based plans.

We need to create a strategy such that the first Order is generated on 19th Jan 2018 with counter reading of 61461. From that point onwards the next reading will be after 2500 hrs i.e. at 63961 then after 1500 hrs at 65461, then again after 2500 hrs at 67961 and then 1500 hrs at 69461 and so on.

I need to understand what I need to enter for Package details in IP11 (Strategy) and once Maintenance Plan(IP42) is created based on the created Strategy then how to schedule in IP10 i.e. what to give in the Start counter reading.

Note: I know how to create Equipment, Task List and Package assignment to Operations for above process

Thanks

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Mar 07 at 05:07 AM

    Hi,

    Can anyone shed some light on my query?

    Thanks

    Faisal

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Faisal,

      You want to have orders generated 1500 - 2500 - 1500 - 2500.

      When you schedule the plan, system will be generating as below screenshot

      So you cannot get the alternate option.

      Alternate option is Multiple Counter Plan, here you need to have separate counter for 1500 and 2500. Upon scheduling system will behave has expected.

      Check this concept in your system

      Regards

      Terence

      capture.png (18.7 kB)
  • avatar image
    Former Member
    Mar 07 at 12:23 PM

    Hi Faisal,

    You will have to create a strategy with package P1- 2500 Hr and P2 - 1500 Hr.

    Now when scheduling the maintenance plan, put start counter reading as 61461.

    Try it and let me know if it answers your query.

    Thanks,
    Ashish