What is the use of Due Date field in MAT01 UI, How we can use this field .

pyhnv.png (23.4 kB)
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Markus Ganser
Dec 08, 2017 at 08:28 AM
0

It is the date, at which the requester expects the Change Request to be completed.