Production order -actual labour time

Hi All,

I need to capture the total labour used for a production order

is there any provision to capture the total labour hours for the production order

Regards

Anand Srinivasan

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Best Answer
    Mar 26, 2008 at 05:57 AM

    1.Go to transaction code coois ( order information system)

    2. In the list give it as Confirmations

    3. In the Profiel give the Standard Profile

    4. Give the Order no / Plant details in the header level

    5. Execute the report

    6. Now you get the details of the Production order

    7. In the layoout get the activity 1 to acitivty 6 with UOM and qty

    8. Do the quantity summation as required this will give you the required result

    do let me know if you have different requirement

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Dear All,

      Thanks for ur help .,

      I can able to get the data as per Sathiskumar instruction to give confirmation header in COOIS

      As per Amit i got the details in AFRU table

      Regards

      Anand Srinivasan

  • avatar image
    Former Member
    Mar 26, 2008 at 05:51 AM

    hi

    u can get from table AFRU

    or u can contact CO person, there is std report for viewing planned cost and actual cost.

    Reward if useful

    Amit

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 26, 2008 at 05:54 AM

    Hi,

    Goto CO02 , enter the prd order no.

    Goto operation overview, double click the opn 0010 , check in qty/ activities tab page.

    System will show the actual required time and confirmed time for each activity ie, setup time, machine time, labour time which you have defined in std value key of routing.

    Like this you can check for each opn 0020, 0030 for a particular order.

    Regards,

    Dharma

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 26, 2008 at 06:27 AM

    Hi,

    1.First you need to define parameters like setup time, machine time and Labour time etc., - OP7B

    2. Define standard value key - OP19.- the standard vaule key determines the meaning of the six standard values( setup, machine and Labour) in the operation.

    3. Assign this standard vaue key in the work center basic data view and maintain rule for maintenance.

    4. Assign this work center in routing of the material.

    5. When you create a production order, this routing is copied.

    6. When you confirm production through CO11n, you can enter setup time, machine time and Labour time etc.,

    Hope this is helpful to you.

    Regards,

    K.karunairaj