Material planning for production equipment

Former Member
0 Kudos

Dear, colleagues,

а customer need to plan some materials not for finished product but for production equipment. Man need to load some reagents in proportion to operating time of equipment and some reagents in proportion to raw material volume. It`s not possible now to assign reagents volumes to finished products volume in BOM.

We have norm of reagents and planned operating time/raw volumes for equipment.

Is any workaround in SAP ERP to create requirements for reagents and involve the requirements in MRP without ABAP and creation equipment as materials?


Accepted Solutions (0)

Answers (1)

Answers (1)

AKK
Explorer
0 Kudos

Dear

I think my suggestion a bit late but Material Quantity Calculation functionality may serve your purpose