Hi all ,
I have FG contains SFG
I am doing backward scheduling .
after MRP , in MD04 the planned order dates and time r as follows :
For FG : date time
Order finish : 30.03.2008 17:30:00
Order start : 23.03.2008 12:50:00,
and for SFG actually the dates the system is giving :
Order finish : 23.03.2008 17:30:00
Order start : 23.03.2008 10:30:00,
Now the requiremnt here is Order finish of SFG should be one day before , that is 22.03.2008 , i am trying with Sch margin Key as :
Flt before prodn : 1 day & float after prodn : 1 day , what i have to use so that i can get one day Gap ?
Regards