Here is my issue..

the requirement is that maintenance calls will be generated at the beginning of every month (using"Time-key date" and package 1 mon ),it is also required that no past calls will be generated

Any idea if Function module: EXIT_SAPLIPM5_002 can be used to meet these requirements? any other suggestion will be appreciated.

Thanks

Add a comment
10|10000 characters needed characters exceeded

Related questions

5 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Mar 23, 2008 at 08:53 AM

    Hi,

    While doing scheduling,give the "Start Date " as per your requirement.

    Regards,

    Santhosh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Mar 24, 2008 at 03:00 AM

    Hi,

    If you are planning for single cycle plan, then for monthly cycle key date start date is enough.

    If you are doing strategy plan with diff frequency then you have to offset the plan for the current month

    Best wishes

    Govind

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Mar 24, 2008 at 09:28 AM

    hi,

    Ram

    i am not getting the meaning of one line please explain that so that we can discuss..

    the line is

    it is also required that no past calls will be generated what is meaning of past calls

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Mar 24, 2008 at 11:32 AM

    Generate a Plan with scheduling Parameters like this,

    If that is Singly Cycle Plan - Start Date should be 1st of every Month (Time)

    Startegy Plan - Give Offset accordingly.

    Call horizon is 100%

    Confirmation required - Select (if required)

    As Mr.Amit has asked, what is that sentence is meant for

    Sam

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Mar 24, 2008 at 05:48 PM

    thanks for the reponse

    The maintanance plan parameters are :

    1.Singly Cycle Plan - Start Date is 01.01.2008

    2.Call horizon is 100%

    3.Confirmation required - Selected

    4.Cycle modification factor=1

    by transaction IP10 push on start and save.

    call Plandate

    1 01.02.2008

    if the call is completd (Black flag) today 24.03.2008 then

    the next call plan date will be 01.03.2008 (that's what I meant "In the past" )

    the IP10 screen be then look like:

    Call Completion Plandate

    1 24.03.2008 01.02.2008

    2 01.03.2008

    the required output was that call 2 plan date will be 01.04.2008 (that what I meant not in the past )

    Also, if I use Shift Factor Late Compl.=100% than the next plandate will 24.04.2008 which also donse not meet the requirment

    that the calls Plan date will be exactly at the 1'st at each month

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      hi,

      I think this is not possible in std. You can skip the call (01.03.08) and proceed with the next call (01.04.08).

      But that may not solve your problem. Experts, is there any user exit available for this issue.

      Sam

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.