HI,

my client have requested for automatic reorder point planning ( mrp type VM), so please provide me with step by step procedure, configuarion, settings required.

what are the required input parameters, how reorder point and safty sotck is calculated by the system and where it is displayed

please provide all useful information in detail regarding mrp type VM

thanking you

arun kumar

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi

when ever you are going for automatic reorder point planning you are supposed to mention the reorder point interms quantity. depending on the consumption of material in future system will calculate the reorder point automatically same will be reflectedd where you have mentioned the repoder point in MRP1 view.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Auto ROP planning - MRP type VM needs forecasting data to be maintained.

Required input parameters

MRP type - VM

Forecasting view to be maintained (Forecast model,per indicator,Hist. periods,Forecast periods etc.)

Cons values,

RLT (MRP 3 view)

Service level (MRP 2view)

Once these values are enetered, execute forecast from MM02 or MP30.

Then you can see in MM02 that ROP and safety stock will be updated.

pls try.

Automatic Reorder Point Planning

In automatic reorder point planning, both the reorder level and the safety stock level are determined by the integrated forecasting program.

The system uses past consumption data (historical data) to forecast future requirements. The system then uses these forecast values to calculate the reorder level and the safety stock level, taking the service level, which is specified by the MRP controller, and the material's replenishment lead time into account, and transfers them to the material master

Regards,

Sheik