Issuing materials to project as a custody

Hi all,

I have a business scenario in construction industry, the customer needs to issue valuated materials to project mvt (221 Q) with regards to the employee(technician) /subcontractor who will use those material (custody) in a project and trace them.

Note: Remaining issued materials can be returned to project stock and release the custody from the person.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Dec 07, 2017 at 02:00 AM

    Hi Mustafa,

    You can create employee(technician) /subcontractor as vendor. If you are using HCM module, then you can extend employee as vendor via PRAA. During goods movement populate vendor code there.

    Here the link for your reference that someone propose to use Internal order to represent person. Of course you can consider to use WBS to represent person.

    Thanks.