Source not included despite source list requirement

Hi,

I have source list box checked in the material master.

I created the Scheduling agreement with out maintaining the source list and the system not asking me for the source list.

But while maintaining the delivery schedules the system checking for the Source list and throwing the error message

as mentioned.

even if I maintain the source list at this moment, It is giving still error message "Source not included despite source list requirement"

I am working on ECC 6.0

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    Mar 19, 2008 at 03:33 PM

    Go to ME01 source list and check the following

    From Date

    To Date

    Vendor

    Purchase org

    Plant

    Agreement no(P.O No)

    Item no:say 10,20 for the material

    G.Ganesh Kumar

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 19, 2008 at 11:09 AM

    friend

    Suggest you to create SA and Schedule line afresh insted of using old SA.

    ENJOY SAP

    Regards

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 19, 2008 at 02:01 PM

    first make sure that your source list date is same as your SA date and did you enter the SA and line item number in the source list.

    if all above is done then check one more thing

    use ME05 tcode and generate the source list.

    Add comment