IBP for Supply calendars

Dec 05, 2017 at 06:56 PM

68

avatar image

Hi all

For the heuristic I want only to create proposals on working days (monday to friday).

How can I achive this since I cannot assign transportation calendars to transportation lanes.

Thanks in advance

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Lingaiah Vanam Dec 06, 2017 at 12:36 PM
0

Hi,

Supply operator generally runs at weekly level. If the customer wants to run at daily buckets supply operator is not consider the calenders (Shifts and Working days), to achieve this workaround solution would be releasing forecast to Monday to Friday.

Best Regards,

Lingaiah