Physical sample linked to 2 inspection lots. Need to assign it to other one

Hi QM experts.

In our process a physical sample got linked to two inspection lots. Screenshot shown below. Now in QPRS table the physical sample is shown linked to the latest one (The one ending with 26100) we need to change this such that it is linked back to the old one and the same is seen in QPRS table.

Any suggestions on how to do this?

qprs.jpg (45.5 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Dec 07, 2017 at 02:21 PM

    Have you gone to QA02 and tried to cancel the lot?

    Inspection Lot-->Functions-->Cancel Lot

    Craig

    Add comment
    10|10000 characters needed characters exceeded

    • Ok. In that case, I'm not sure how much I can help you since it's using all custom code. Standard SAP uses inspection type 15 to reinspect previous pulled samples.

      So my guess is that you might be able to use QA02 do cancel the unwanted lot. But outside of that I have no idea how it will impact anything else you have going on since it appears to be a custom design.