PR for each Reservation

Hi,

I have got several Order Reservations in a day. I find that MRP generates a single PR for the day with Qty = Sum of all Reservation Qty. But what I need is PR for each Reservation.

Is there any customizing or Master data steps that I am missing ?

Thanks.

Raj

Add a comment
10|10000 characters needed characters exceeded

Related questions

6 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Mar 17, 2008 at 02:28 PM

    Hi,

    Use Tcode OIOE and remove collective Reqstn for your particular Order type and save the configuration.

    Please check and confirm ur commands,.\

    Regards

    Sendil

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Mar 18, 2008 at 10:03 PM

    Hello Raj,

    I really don't understand why you want to do this.

    Could you explain the business process behind this.

    Thank you!

    btw - I think it's impossible

    Best regards

    Stephan

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Stephan,

      Thanks again.

      I have already configured the Stor. Locns. as MRP Areas for exclusive MRP. This way, I have ensured each Stor. Locns. are planned independently.

      Your question is valid. But the Stor. Locns. are geographically far apart and hence I need to monitor Stock in Transit after dispatch from WH. So Goods Issue from WH against the Reservation (which is a single step transfer) didn't fit the business process.

      Any other thought ?

      Raj

  • author's profile photo Former Member
    Former Member
    Posted on Mar 19, 2008 at 03:21 AM

    Hi,

    I think the problem lies with material master settings. The field "lot size" under tab "Lot size data" in MRP1 of material master decides the consolidation of procurement process. If you give indicator "EX" ( Lot by lot indicator) there will be purchase requisition for each reservation. Presently the indicator could be "TB" (Daily lot size).

    Please check this and set appropriate settings.

    Muraleedharan.R

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Mar 19, 2008 at 08:17 AM

    Hi Raj,

    Go to materail master and change;

    1. MRP1 : - The lot size should be TB.

    2. MRP4 : - The "Individual/coll" should be selected as "Individual requirements only"

    Let me know the progress,

    Best Of Luck,

    Regards,

    Shyamal H. Joshi

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Shyamal,

      I did what you mentioned but the result is still a single PR for the day covering various Reservations. (TB being daily lot size).

      Let me know if there is any other alternative.

      Thanks.

      Raj

  • author's profile photo Former Member
    Former Member
    Posted on Mar 19, 2008 at 12:55 PM

    Hi ,

    make the setting as given below in material.

    MRP1 >Lot size date >select EX(Lot for Lot order quantity)

    MRP4 -->Indivitua/Coll --> Select Indivitual.

    I have tested and it generated multiple PR wrf Reservation.

    Let me know..

    Regards

    Sendil

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Senthil,

      I am not getting the same result as you do i.e., generation of single PR for each Reservation through MRP based on Lot Size = EX and Individual / Collective reqmts = 1. It is still a single PR covering all Reservations in a day.

      Could you pls tell me if there are any other settings required in the config ?

      Thanks.

      Raj

  • author's profile photo Former Member
    Former Member
    Posted on Mar 23, 2008 at 04:48 AM

    Hi Raj,

    If reservation falls on same Period (ie same date on a month ) ,then system groups requirement quantities from the same date together in one procurement proposal even if u set EX.

    Regards

    Pradeep

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.