Skip to Content
0
Former Member
Mar 14, 2008 at 07:52 AM

Factory Calender assigned to Plant & resource/Work center

1657 Views

Hello,

If we have assigned the Factory Calender "XX" which has 5 working day(Monday to Friday) with no Special rules & no Holiday Calender to Plant & "YY" Factory Calender to Work center which has 365 days working with no no Special rules & no Holiday Calender.Now, when MRP creates Planned Orders for FERT material It did not create it on Weekends(i.e. on Saturday & Sunday) though the factory calender assigned is "YY" (which has 365 days working )in work center.Why?

Actually it should have consider the Work center assigned Calender for Capacity planning & Schedulling purpose.

If I assign the Factory Calender "YY" to plant then it will create the procurement proposal on weekends which is not acceptable to external procurement MRP Controller as plant office works only 5 days.

Please guide.