on 03-13-2008 12:01 PM
I need the tables form where I can pick the planned labour & overhead cost for a production order.
i want to calculate my planned labour cost for all operations in my production order. how can i retrive form the tables and how the actual planned cost gets calcualted. where can i see the overhed calcualtion of the material and labour.
please suggest.
venkatesh
Hi venkatesh,
There is a help transaction RKACSHOW, to display all the costs related information for a CO-Object, in your case the oder. The involved table name is listed indirectly too. For example COSSA for the table COSS, and COSPA for table COSP and so on.
Kind regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Venkatesh,
Please see Tables PLPO, AFVC & AFRU.
Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.