Transfer ERP HCM data per IDoc

Hello,

i want to distribute data from ERP HCM with report RHALEINI.

The IDoc is a reduced IDoc of HRMD_A.

It's working fine but i get almost 500 resulting IDocs and it would be better to have just one IDoc.

Is this possible?

If it's not possible there are 2 problems:

1) Not all IDocs receive at XI

2) I have to collect all IDocs and will need a some kind of correlation and don't want to use BPM (only if it's there is no other way)

Why do i get so much IDocs anyway? Has it to do with a maximum size of IDocs?

Regards

Patrick

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Mar 13, 2008 at 12:49 PM

    Hi

    on the screen of the report you have Paralle processing

    In that there is 'Number of objects per process'. By default this is 200. If you increase this number the number of segment in an Idoc will increase and you will have lesser IDoc

    Also, you can use other input criteria to filter the data like object type P will send only the person accross.

    Regards

    Vijaya

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hello,

      filtering the infotypes didn't changed so much in my case.

      Seems that it's not possible to reduce the number of IDocs to one.

      I will try if IDoc packaging could help.

      Thanks