Is there any any FM or method available to change the Staging Bay in the ODO line item to some other than the system determined value.

Actually my requirement is that user should be able to change the Staging as per his need after reviewing the system proposed value.

Thanks

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Dec 11, 2017 at 01:27 PM

    Hi Akhil,

    TU is assigned to the delivery item ? If yes, you can change staging in standard shipping cockpit tool.

    Kind Regards,