on 12-05-2017 5:57 AM
We are about to use commitment in purchasing while keeping budget on internal orders. Copy of account assignment F is used where consumption is not triggered in order to keep the stock after MIGO.
But after MIGO, system do reduce commitment amount as well as allotted which likeably happening due to lack of actual posting.
Our requirement is to create actual posting on order during MIGO under commitment budget with the help of standard functionality.
Please Note: We are not using FM.
Hi,
In CO you don't have Commitment or Payment budget; these are terms of PSM-FM. In CO you have just one budget, posted on internal order and/or WBS. A purchase order will create commitment, while GR will deduce it and make actual consumption. This is standard behaviour... Any deviation from this scenario won't be standard.
Regards,
Eli
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.